2005 Board of Commissioners scoreboard: projects and funding

By Mike Cross
Posted Wednesday, January 11, 2006

e-mail E-mail this page   print Printer-friendly page

PUBLIC SCHOOLS:

1. SILER CITY ELEMENTARY SCHOOL - New - $17 million - COP. Estimated start: Summer’06. Estimated completion: 2009.

2. NE CHATHAM MIDDLE SCHOOL - New - $18.5 million - COP. Estimated start: Fall’07. Estimated completion: Dec.2010.

3. NE CHATHAM HIGH SCHOOL - New - $43.9 million - Nov.’06 Bond Vote. Estimated start:_if approved-Jan.’09. Estimated completion: Dec.2011.

4. JORDAN MATTHEWS HIGH SCHOOL - New Cafeteria - $5.4 million – COP. Estimated start: Mar.’06. Estimated completion: June’07.

5. HORTON MIDDLE SCHOOL - 5th and 6th Grade Bldg. - $3.9 million - COP. Estimated start: July’06. Estimated completion: Jan.’09.

6. SCHOOL IMPACT FEE STUDY – SIF established fall ’99 (max allowed $3,500). BOC set fee at $1,500 – BOC raised fee to $2,900 in’05. Teschler –Dice reviewing to up-date SIF Cap. Estimated start:_ONGOING_ Estimated Report: TBD.


CENTRAL CAROLINA COMMUNITY COLLEGE:

1. BIOTECH / LIBRARY BUILDING - Pittsboro - New -$3.7 million - COP. Estimated start: Apr.’06. Estimated completion: Mar.’08.

2. JOINT CCCC and CHATHAM COUNTY LIBRARY - Pittsboro - $5 million - COP. Estimated completion: Mar.’08.

3. JOB TRAINING CENTER - New - Siler City - Business Park - $3.1 million - COP. Estimated start: Apr.’06. Estimated completion: Mar.’08.


BUSINESS PARK:

1. INFRASTRUCTURE - Roads, Water, Sewer, etc. - $6.7 million - COP. with (new) CCCC Campus ( start_?_), (new) Chatham Hospital (start Jan.’06), (new) Juvenile Center ( start Mar.’06) and realistic Economic Development opportunity. Estimated start: Jan.’06. Estimated completion: June’07.


GOVERNMENT FACILITIES:

* SOCIAL SERVICES BUILDING - Expansion - Pittsboro - $4.2 million - COP. Estimated start: Jan.’06. Estimated completion: Dec.’07.

* JUDICIAL FACILITY - New - Pittsboro - $7.5 million - COP. Estimated start: Jan.’08. Estimated completion: Dec.’09.


WATER SYSTEM IMPROVEMENTS:


* PEA RIDGE TRANSMISSION LINE - 16 inch (possibly 24”depending on Harnett) transmission line to SE Water District and inclusive new lines. $8 million - NCDENR-SRF low interest loan. Estimated start :_ 24”decision ?_ Estimated completion: _ JUNE ’06__.

* N. CHATHAM TANK BOOSTER STATION/WATER MAIN to Governor’s Club tank and proposed MANN’S CHAPEL RD. tank. $2.5 million – CHATHAM CO./ Availability Fees. Estimated start: IN PROGRESS. Estimated completion: FEB.2007.

* N.CHATHAM - HIGH SERVICE - PUMP STATION - upgrade. $0.5 million – NCDENR-State Revolving Fund - low interest loan. Estimated start: bid Feb. ’06. Estimated completion: TBD.

* SILK HOPE SCHOOL WATER MAIN – 12”on 64 West and 8”on Silk Hope Rd. $1.1 million - FUNDING? Plus_20+__ sign ups @ $500. Estimated start: IN PROGRESS. Estimated completion: APR. ‘06.

* WESTERN TRANSMISSION LINE - 16’ transmission line from Moncure to 64 West with a 12”transmission line to the SW WATER DISTRICT including 1 booster pump station and 1 elevated 0.5 mg tank. $11 million – NCDENR-SRF low interest loan. Estimated start: bid Apr.’06. Estimated completion: TBD.

* SOUTHEAST WATER DISTRICT - 23 miles of main and 1 elevated tank. $3.6 million – USDA Rural Development loan – Customer fees. Estimated start: Summer’06. Estimated completion: MAR.’07.

* SOUTHWEST WATER DISTRICT - 48 miles of main and 1 elevated tank. $6.3 million - USDA Rural Development loan and grant – Customer fees. Estimated start: ’07. Estimated completion: ’08.

* WATER TREATMENT PLANT –East Jordan Lake – upgrade pumping capacity from 3mg/day to 7mg/day. $6.7 million – County Loan and Availability Fees. Estimated start: Summer’06. Estimated Completion: TBD.

* SOUTHERN SUPREME – Fruit Cake Plant – 6” main from Sanford with 35 en-route customers. $0.5 million - NCDOC – CDBG / ED Grant $240,000 - Local match of $179,000 – eventually to USDA. Estimated start: Summer’06. Estimated completion:_Fall ‘06.

* WATER TAPS…for existing lines within water districts. $123,000 due to underestimating early sign-up fees. $47,000 customer pre-paid fees and $76,000 County support. Estimated start: ONGOING. Estimated completion: 1/4 complete.

* WEST JORDAN LAKE INTAKE STUDY…for location and water allocation. $Hourly Rate -- HOBBS-UPCHURCH -- County funds. Estimated start: ONGOING. Estimated report: TBD.

SEWAGE /SEWERAGE IMPROVEMENTS

1. GOLDSTON SEWERAGE LINE …from Sanford –100,000 gallons per day. $1.2 million - project and funding to be determined.

2. COUNTY SEWAGE TREATMENT STUDY…for location, discharge permitting and estimated cost by HOBBS-UPCHURCH. $Hourly Rate plus USDA-Rural Development –1/2 to ½. Estimated start: ONGOING. Estimated Report: TBD.

LAW ENFORCEMENT IMPROVEMENTS

1. REGIONAL JAIL FACILITY / TRANSPORT STUDY…possibly partner with Lee and Moore on Regional Jail and Prisoner Transport. $8,000 - Chatham share of study cost. Estimated start: ONGOING. Estimated report: TBD.

 
Related info:
Mike Cross' Weblog
e-mail E-mail this page
print Printer-friendly page
 
 
 
2005 Board of Commissioners scoreboard: projects and funding
Chatham County Commisioner Mike Cross shares his viewpoints with citizens on his weblog.


Related info:
Mike Cross' Weblog
 
Opinion

Got Feedback?
Send a letter to the editor.

Subscribe
Sign up for the Chatham Chatlist. Find out what your friends and neighbors are saying about what's going on in Chatham County.

Advertise
Promote your business at chathamjournal.com

Subscribe now: RSS news feed, plus FREE headlines for your site